Plan the Transfer-Switch and Switchgear Boundary

Automatic transfer switches (ATS) change a load’s connection between designated power sources when control logic identifies a need to transfer. Their coordination with new switchgear begins by establishing where the ATS sits in the distribution system and which equipment provides source protection, load protection, isolation, and control. A one-line diagram should show normal and alternate sources, the transfer device, downstream loads, and relevant upstream and downstream protective devices. This helps reveal whether the ATS is part of a switchboard assembly or a separate piece of equipment, and clarifies which supplier is responsible for each interface.

For Austin and Central Texas projects, early coordination can also reduce avoidable design and procurement changes. Share the one-line diagram, design criteria, load information, and equipment boundaries with the switchgear manufacturer while the arrangement is being developed. The manufacturer builds new equipment in the USA with all-American components and can develop custom assemblies to specification. That does not replace project engineering: a qualified electrical professional must confirm the design and applicable requirements for the actual installation.

Select the ATS Around the Sources and Load

ATS selection depends on the electrical system, source characteristics, load behavior, and the required transfer sequence—not just the nameplate of a connected switchboard. Confirm system voltage, phase and frequency, load current and characteristics, available fault current, grounding arrangement, and whether the intended transfer is open, delayed, or another specified sequence. Determine whether the load can tolerate an interruption and whether particular loads require separate transfer arrangements. The ATS and its enclosure or assembly must be suitable for the installation conditions, but acceptable ratings and construction must be verified for the specific project.

Provide operating scenarios for both sources, including expected source limitations and any load-shedding or priority requirements. Identify whether loads include motors, electronic equipment, or other devices with starting or restart considerations. Do not assume an ATS rating, withstand capability, enclosure type, or product listing from a general description. The project engineer should confirm selection against the system study, equipment specifications, applicable standards, and authority requirements. These inputs help determine whether the proposed switchgear arrangement can accommodate the transfer device and its connections.

Coordinate Protection and Fault Response

Protection coordination requires more than placing an ATS between two sources. Identify protective devices on each source and on the load side, their functions, and the fault-current information used to select and coordinate them. Review how the transfer device and upstream protective equipment respond to faults, and whether a fault on one source or downstream circuit affects transfer logic. The design team should evaluate selective coordination where required by the project, without assuming that a particular device combination or setting will achieve it. Final device selection and settings require qualified engineering review using project-specific data.

Provide available fault-current values at relevant equipment locations, source and transformer information, protective-device data, and any completed coordination or arc-flash studies when available. Confirm responsibility for protective devices furnished within the ATS, switchgear, or elsewhere in the distribution system. If studies or source data are still pending, identify them as open design inputs rather than treating provisional assumptions as approved. Switchgear ratings and applicable standards depend on the assembly design and project conditions; UL 891 applies to suitable switchboard assemblies, not automatically to every ATS or switchgear configuration.

Define Controls, Interlocks, and Operating Modes

Document how the ATS detects source status, initiates transfer, and determines when retransfer is permitted. Decisions may include time delays, preferred-source logic, manual operation, test modes, alarm indications, and whether retransfer is automatic or requires operator action. These choices affect control wiring, device interfaces, and the operating sequence presented to facility staff. Identify who supplies each control component and which signals must be exchanged with switchgear, generators, building controls, or other equipment. Signal names, contact types, and control-power requirements should be established from the actual designs.

Interlocks should support the intended operating sequence and prevent prohibited source connections where applicable to the system design. Specify the normal, alternate, test, maintenance, and failure states that the design must address; do not infer that an ATS provides a particular interlock or bypass arrangement unless it is confirmed. The engineer and equipment suppliers should document the sequence of operation and review it together before release. Clear responsibilities for control logic, field wiring, and interface terminals help avoid gaps between separately furnished equipment.

Plan Interfaces and Verification Before Release

A practical interface schedule identifies power connections, control wiring, communication points, terminal locations, required signals, and the party responsible for each connection. Confirm the physical arrangement, conductor entry, access, clearances, environmental conditions, and any separation needed between power and control wiring. These details matter when integrating an ATS into a custom switchgear assembly or coordinating separate enclosures. Review drawings for equipment boundaries, connection points, and control diagrams before approving fabrication; changes made after release can affect layout, wiring, and procurement timing.

Define verification expectations in the project documents. Depending on the design and contract, reviews may include drawing checks, inspection of the assembled arrangement, and functional checks of transfer logic and indicated signals. Establish test conditions, acceptance criteria, witness responsibilities, and how simulated source conditions will be handled; do not assume a particular factory or site test is included. Field installation and commissioning responsibilities must be assigned by the project team. Never use an informal test procedure on energized equipment; testing and commissioning should follow approved project procedures and qualified-professional oversight.

Prepare a Complete Procurement Package

To request new switchgear coordinated with automatic transfer switches, provide the current one-line diagram, load schedule, source details, equipment specifications, fault-current information, control sequence, interface schedule, and installation constraints. Note which inputs are final and which remain subject to engineering confirmation. Also identify the required submittal information, applicable project standards, desired ship-to location, and procurement milestones. A complete package helps the manufacturer assess the proposed assembly, flag unresolved interfaces, and determine a project-specific lead time without relying on assumed ratings or generic availability.

Before placing an order, resolve responsibility for the ATS, protective devices, controls, interlocks, wiring, and any separate equipment. Ask for the proposed scope and drawings to show those boundaries, then route them to the electrical engineer and other responsible reviewers for approval. The manufacturer can build custom assemblies to specification and ship nationwide; shipment planning should be coordinated with the project schedule and site receiving requirements. Confirm final ratings, construction, standards applicability, and acceptance requirements in the approved documents before authorizing production.

Project specification checklist

Use this checklist to organize the details for a project-specific review. Final ratings, applicable standards and equipment selections depend on the approved design.

ItemWhat to confirm
System and load dataConfirm voltage, phase, frequency, grounding, load characteristics, and source operating conditions from project documents.
Fault and protection basisProvide available fault-current data, protective-device information, and required coordination or study criteria.
Transfer sequenceSpecify transfer and retransfer logic, time delays, operating modes, alarms, and any load-priority requirements.
Interlocks and signalsDocument permitted operating states, interlock requirements, control power, signal types, and interface ownership.
Physical and procurement interfacesConfirm equipment boundaries, layout and connection constraints, submittal approvals, ship-to details, and project-specific lead time.