Why Section-to-Section Bonding Needs Attention

New switchgear may be transported in multiple shipping sections and joined at the installation site. The electrical and mechanical interfaces between those sections must preserve the grounding and bonding arrangement defined for the complete assembly. A joint that appears aligned is not, by appearance alone, evidence of adequate bonding continuity. The design needs to address how conductive paths cross the shipping breaks and how the sections are assembled.

For project teams, this affects more than equipment fabrication. The switchgear drawings, grounding plan, shipping arrangement, site connection details, and assembly instructions need to tell a consistent story. Early review can identify where a field-installed connection is required, who provides it, and what must be checked before the equipment is placed into service. The applicable requirements depend on the equipment design and project.

Inputs That Define the Bonding Arrangement

Provide the manufacturer with the project grounding philosophy, equipment configuration, one-line diagram, physical arrangement, and the intended location of each shipping break. Identify the site grounding conductor connection point and any project requirements for bonding to building steel or other conductive systems. Relevant details may also include system voltage, available fault-current information, the protective-device scheme, and the environment in which the assembly will be installed. Qualified electrical professionals should establish and review these inputs.

The required bonding path cannot be selected from a general description such as “standard grounding.” The equipment design and its applicable standards, project specifications, and authority requirements govern the arrangement. Confirm whether the specification calls for particular materials, connection methods, inspection records, or tests. Do not assume that a construction detail, product listing, or rating applies to every configuration; applicability must be verified for the proposed assembly.

Interfaces at Each Shipping Break

Review every interface where sections meet, including the main grounding bus or other designated bonding conductors, structural metal, and any connection points identified in the drawings. The design should make clear which components are factory-installed and which connections are completed during field assembly. Where conductors, splice plates, fasteners, or contact surfaces are part of the intended path, their location and assembly sequence should be shown in the approved documentation.

Shipping and installation can affect access to these interfaces. Confirm that section orientation, lifting and handling plans, adjacent equipment, and the final lineup position will not obstruct the specified joints. The project team should also clarify responsibility for supplying and installing any field components, preparing interfaces when required, and inspecting completed connections. Avoid substituting hardware or changing the joint arrangement without review by the responsible design and equipment professionals.

Design Decisions for the Complete Lineup

Bonding decisions should be made for the complete installed lineup, not as isolated details on individual shipping sections. The design review should establish the intended continuity path, how it connects to the site grounding system, and how section joints remain accessible for assembly and inspection. Consider the specified fault-current duties and protective scheme when confirming conductor and connection design; do not infer an acceptable rating without project-specific engineering review.

Custom assemblies can be developed to project specifications, but the approved drawings must resolve interfaces before release for manufacture. Confirm section boundaries, connection locations, required clearances, and the treatment of any removable or separately assembled components that affect the bonding path. For suitable switchboard assemblies, UL 891 may be relevant; it does not automatically apply to all switchgear or establish that every field interface is correct. Applicable standards and listing status require verification.

Assembly, Inspection, and Verification

Before field assembly, compare the delivered sections and connection materials with the approved drawings and assembly instructions. Check section identification, orientation, joint locations, and access to the specified bonding interfaces. Complete each connection using the documented method and any stated preparation or tightening requirements. If parts are missing, damaged, contaminated, or inconsistent with the instructions, pause and obtain direction from the responsible project parties rather than improvising a connection.

Agree in advance on how continuity will be inspected or tested, who is responsible, what procedure and acceptance criteria apply, and how results will be recorded. A continuity check can support verification, but the suitable method and interpretation depend on the design and project requirements. Testing should be performed by qualified personnel using an approved procedure, with equipment in an appropriately safe condition. The project’s qualified professionals and relevant authorities determine required checks and acceptance.

Procurement Review and Practical Closeout

When requesting new switchgear, include the shipping-section plan and bonding requirements with the specification package rather than waiting until delivery. Ask for drawings that identify the intended section-to-section interfaces, factory-completed work, field connections, and assembly sequence. Confirm that the proposed arrangement matches the site layout and grounding design, and resolve responsibility for any field-supplied items before procurement is finalized. A manufacturer can review custom assemblies to specification, subject to project details and design review.

Before shipment, coordinate drawing approval, section markings, connection documentation, and any agreed verification records. At the site, retain the approved documents and completed inspection or test records with the project closeout package. For Austin and Central Texas projects, coordinate shipment timing, receiving, storage, and the sequence for moving sections into the electrical room with the project team; these logistics depend on the site plan. Provide complete inputs early to support a practical schedule, since lead times are determined by project.

Project specification checklist

Use this checklist to organize the details for a project-specific review. Final ratings, applicable standards and equipment selections depend on the approved design.

ItemWhat to confirm
Shipping-section layoutConfirm section boundaries, orientation, lineup sequence, and the location of every joint that affects bonding continuity.
Grounding requirementsProvide the project grounding philosophy, site connection points, specification requirements, and applicable authority criteria.
Bonding interfacesIdentify the intended conductive path, connection components, factory work, field work, and assembly instructions.
Engineering basisHave qualified professionals verify design duties, protective scheme, applicable standards, and any listing requirements.
Verification and recordsAgree on inspection or test method, responsibility, acceptance criteria, and documentation before assembly.