Define the Interlock’s Purpose

Interlock coordination for new switchgear begins by stating which unsafe or unintended operation the design is meant to prevent. Electrical interlocks use control circuits or logic to permit or block an operation; mechanical interlocks use physical mechanisms to constrain operating sequences. Depending on the equipment and system design, interlocks may coordinate breakers, disconnecting devices, access doors, or alternate sources. They are not a substitute for protective devices, operating procedures, or a complete protection and coordination study.

Describe each intended function in plain language, including the normal sequence and the condition that must prevent an operation. Identify whether the requirement is driven by system operation, equipment arrangement, a project specification, or a safety assessment. This early definition helps distinguish an interlock from a protective trip or alarm, reducing ambiguity before the switchgear design and control scheme are developed.

Gather System and Operating Inputs

Interlock decisions depend on the electrical one-line diagram, source and tie arrangement, equipment boundaries, control-power design, and the operating modes the facility expects. Provide the intended normal lineup, permitted alternate lineups, transfer sequence, and any restrictions on paralleling sources. Document what operators may initiate locally or remotely, what conditions must be verified first, and what should happen if control power or a status signal is lost.

Project teams should also identify equipment tags, device positions and auxiliary contacts available for logic, relevant protection functions, and interfaces with upstream or downstream equipment. Confirm who owns each signal and how it will be represented in drawings and controls documentation. Ratings, device construction, applicable standards, and environmental or enclosure requirements must be established for the specific project; none should be inferred from an interlock description alone.

Choose Electrical, Mechanical, or Combined Means

Selection turns on the operation being controlled, the equipment’s physical arrangement, the required sequence, and the consequences of an incorrect operation. Electrical logic can coordinate permissive signals and control commands across a defined scheme. Mechanical interlocks can constrain movement through physical relationships between devices. Some designs may use both, but the project must establish how each method functions and which conditions it can actually verify.

Document the operating states, permissive conditions, blocking conditions, and response to abnormal or indeterminate status. For electrical schemes, clarify signal source, contact state, control-power assumptions, and behavior on loss of signal. For mechanical arrangements, confirm which devices are linked, the permitted sequence, and how the mechanism aligns with the equipment configuration. Qualified electrical professionals should assess the design against the application and applicable requirements rather than treating either method as universally suitable.

Map Interfaces and Resolve Conflicts

An interlock rarely belongs to one device alone. Map connections among switchgear sections, breakers, transfer equipment, protective relays, remote-control systems, and operator interfaces where they are part of the project. For each interface, identify the responsible design party, signal or mechanism, source of position information, and documentation deliverable. Mark boundaries where another supplier’s equipment or site control system must provide a permissive or status indication.

Review the proposed sequence against protection functions and the facility’s operating philosophy. An interlock should not unintentionally defeat a trip function, permit an unacceptable source condition, or create a control dependency that is absent from the approved design. Record unresolved assumptions and obtain decisions from the responsible parties. Coordination is project-specific; the required standards and authority reviews depend on the equipment design, installation, and jurisdiction.

Document and Verify the Sequence

Capture the agreed behavior in coordinated documents: an interlock matrix or sequence narrative, one-line and control schematics, device and signal lists, and relevant operating instructions. Use consistent equipment tags and explicitly show normal, alternate, blocked, and fault states. Include expected indications and alarms where required by the design. A reviewer should be able to trace each permitted operation to its necessary conditions and see what happens when a condition is absent.

Before procurement is finalized, agree how the design will be reviewed and verified. Project-specific checks may include drawing review, inspection of mechanical relationships, and functional testing of control logic and interfaces under defined, safe conditions. Identify test boundaries, expected results, responsible participants, and records to retain. The verification plan must match the approved design and should not rely on testing energized equipment as a routine way to discover sequence errors.

Prepare a Procurement-Ready Interlock Package

For a new switchgear request, send the manufacturer the current one-line, equipment schedule, operating sequence, control-power information, interface responsibilities, and any owner or engineer interlock requirements. Flag decisions still open, such as remote operation, alternate lineup restrictions, signal ownership, and expected response to loss of status. Ask the design team to identify assumptions and confirm which interlock functions are included in the proposed assembly and which depend on external equipment or controls.

Review the resulting submittals against the operating narrative before approving fabrication. Check tags, contact states, sequence diagrams, interfaces, and verification criteria together; a mismatch between documents can leave an otherwise complete assembly difficult to operate as intended. Resolve comments with the responsible electrical professionals and relevant authorities. Clear, approved inputs give procurement a traceable basis for custom equipment and help teams coordinate delivery planning without presuming a particular rating, listing, lead time, or site service.

Project specification checklist

Use this checklist to organize the details for a project-specific review. Final ratings, applicable standards and equipment selections depend on the approved design.

ItemWhat to confirm
Operating sequenceConfirm normal and alternate lineups, permitted switching order, blocked operations, and source-paralleling restrictions.
Interlock methodSpecify the required electrical logic, mechanical constraint, or combination, with the function each must perform.
Signals and control powerIdentify signal owners, device status contacts, control-power assumptions, and behavior on loss or uncertainty.
External interfacesDefine boundaries and responsibilities for connections to relays, transfer equipment, remote controls, and other suppliers.
Documents and verificationAgree on the interlock matrix, drawings, sequence review, project-specific checks, expected results, and retained records.